June 2, Day 33 of 45 Day Countdown

Items in bold signify things to do asap!

  1. Protect refinished floors on first, stairway, and second floor hallway with carpenter paper

  2. Remove dust from upstairs bedrooms and bath; lay carpenter paper to reduce dust wherever possible

  3. Install kitchen cabinets, plumbing, remaining electricity

  4. Complete drywall

    • doorways, walls (kitchen, dining room, upstairs bathroom, Charlotte’s bedroom), ceilings (dining room, living room)

    • closet/powder room: postpone to after move-in

  5. Install bathroomtile floor, bathroom vanity, medicine cabinets, toilet, etc.

  6. Complete basement floor epoxy

    • CP’s office

    • laundry room

  7. Install doors and molding to one degree or another in all bedrooms, upstairs bathroom, laundry room, basement, stairway, and closet/powder room: postpone to after move-in

  8. Retrofit vintage hardwood door with 3/4 lite for front door: postpone to after move-in

  9. Install new window in kitchen

  10. Build master bedroom closet: postpone to after move-in

  11. Landscape as much as possible

  12. Do the least amount of harm to ourselves and to the twin!

  13. Prime Ceilings and Walls

    • second floor: master bedroom, office, main bath, hallway, Charlotte’s bedroom, Theo’s bedroom

    • first floor: living room, dining room, kitchen

  14. Paint Ceilings and Walls

    • second floor

    • first floor

  15. Tear down kitchen ceiling

  16. Replace kitchen ceiling: why drywall when the newly exposed beams are so gorgeous?